In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):
A . The delay must affect the critical path.
B . The delay must be concurrent with the delay attributable to both parties.
C . The delay must not cause monetary harm to the defendant.
D . The delay must affect the contractor’s planned construction schedule.
Answer: A