Toward the end of the Iteration, the Product Owner raises a red flag stating there is an additional requirement that needs to be added to the current Iteration. The Agile Team could handle the requirement if they work late and over the next weekend. What should the Scrum Master do?

Toward the end of the Iteration, the Product Owner raises a red flag stating there is an additional requirement that needs to be added to the current Iteration. The Agile Team could handle the requirement if they work late and over the next weekend. What should the Scrum Master do?
A . Meet with the team and if they agree to work overtime, accept the work
B . Talk to the Product Owner, compare the new work to existing backlog priorities, and negotiate a sustainable solution
C . Accept the work and extend the Iteration, informing other teams about the delay in delivery of other committed stories
D . Refuse the new requirement because it is too late to accept requirements at this point in the Iteration

Answer: B