True or False: Product Owners must specify complete acceptance criteria for a Product Backlog item before the Developers can select the item in Sprint Planning.
True or False: Product Owners must specify complete acceptance criteria for a Product Backlog item before the Developers can select the item in Sprint Planning.
A . TRUE
B . FALSE
Answer: B