Which 2 statements correctly define a Business Case risk which should be recorded under the Major risks heading?

Which 2 statements correctly define a Business Case risk which should be recorded under the Major risks heading?
A . Operational costs will increase as a result of the recruitment campaign.
B . The prepared calendar pack is to be delivered to the printers by the first week in December.
C . If the calendar quality is poor customers will not use it, creating the reverse effect and reducing orders further.
D . If any competitors launch a calendar at the same time this will reduce the impact of the MNO calendar and benefits will be reduced.
E . Staff morale will improve as a result of the promotional calendar.

Answer: CD