Which action demonstrates application of the ‘manage by exception’ principle?

Checkpoint reports are being produced monthly. A week after the last checkpoint report was prepared, the team responsible for developing the ‘classroom-based training materials’ have realized that they will not be able to deliver the materials to the accreditor by the work package completion deadline.

Which action demonstrates application of the ‘manage by exception’ principle?
A . The team manager reports the issue in the next checkpoint report.
B . The team manager immediately produces an exception plan to replace the current plan.
C . The team manager immediately reports the issue to the project manager.
D . The team manager raises a risk that the deadline may be missed.

Answer: C

Explanation:

Reference: http://prince2.wiki/Manage_by_exception