Who should approve this update?

The project is at the end of stage 4. The project manager has changed the benefits management approach. It now includes all the activities necessary to measure the increased revenue.

Who should approve this update?
A . Corporate management
B . Project board
C . Project assurance
D . Project manager

Answer: B

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments