Who should approve the external supplier’s team plan?
The development of the ‘e-learning course’ will be outsourced to an external supplier and their key members will join the project management team. The supplier wants to keep their work processes confidential and not share these with ABC Company. ABC Company has agreed.
Who should approve the external supplier’s team plan?
A . Senior supplier
B . Project manager
C . Supplier assurance
D . Corporate, programme management or customer
Answer: D
Latest PRINCE2Practitioner Dumps Valid Version with 282 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments