Which statement about stages is true?
Which statement about stages is true?
A . Management stages should be of the same duration
B . The use of technical stages is mandatory
C . The use of management stages is mandatory
D . Management stages are driven by specialist teams
Answer: C
Explanation:
PRINCE2® mandates the use of management stages in project management. These stages are critical control points used by the Project Board to review progress, assess risks, and make decisions about the project’s future. This structure allows for regular monitoring and controlling of the project by breaking it down into manageable sections.
Reference: PRINCE2® Foundation official documentation and study materials.