Which does the Executive need to ensure is in place before the project is initiated?
Which does the Executive need to ensure is in place before the project is initiated?
A . All Work Packages are authorized
B . An understanding of how the project will contribute to corporate objectives
C . The Project Plan has been approved
D . The Project Initiation Documentation is complete
Answer: B
Explanation:
Before initiating a project, the Executive in PRINCE2 needs to ensure there is a clear understanding of how the project will contribute to the corporate objectives. This alignment is crucial for justifying the project’s existence and ensuring it has a clear business purpose and expected benefits that support the organization’s strategic goals.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources