Which of the following baselines is typically established after completion and approval of system requirements?
Which of the following baselines is typically established after completion and approval of system requirements?
A . Product
B . Allocated
C . Functional
D . Development
Answer: C
Explanation:
The functional baseline is typically established after the completion and approval of system requirements. This baseline includes the functional requirements and specifications that describe what the system is supposed to do. It serves as a reference point for further development and testing, ensuring that all subsequent work aligns with the agreed-upon functional requirements.