which options do you have to exclude a material from the MRP run?
in your Plant, MRP is activated.
which options do you have to exclude a material from the MRP run? Note: there are 2 correct answers to this question.
A . Use a specific material status
B . Use a specific material group
C . Use a specific MRP type
D . Use a specific MRP list
Answer: A C
Explanation:
You can exclude a material from the MRP run by using a specific material status or a specific MRP type. A material status is a user-defined indicator that can be assigned to a material master record to control the procurement and planning activities for the material. For example, you can define a material status that blocks the material from being planned by MRP. An MRP type is a parameter that defines how a material is planned by MRP. For example, you can use the MRP type ND (No Planning) to exclude the material from the MRP run.
Reference: [SAP S/4HANA Production Planning and Manufacturing Certification Guide], page 87; [SAP Help Portal: Material Status] and [SAP Help Portal: MRP Type].
Latest C_TS422_2023 Dumps Valid Version with 80 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund