Should this risk be recorded as an external non-systemic risk within the Strategic Outline Case?

Using the Scenario, answer the following questions about scoping the proposal and preparing the Strategic Outline Case for the Pittville project.

Decide whether the approach is appropriate for stage 1, and select the response that supports your decision.

There is a risk that the local planning authority may reject proposals for development of the Old Fire Station Headquarters site. This will cause delays to the project.

Should this risk be recorded as an external non-systemic risk within the Strategic Outline Case?
A . No, because risks should be identified in the Outline Business Case.
B . No, because this is a service risk associated with the design and build phases of the project.
C . Yes, because the local planning authority is an external organization.
D . Yes, because changes to the Old Fire Station Headquarters site will affect the environment.

Answer: C