It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.

It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.

Reason

BECAUSE

The Solution Development Team is responsible for planning the detail of all the work of each Timebox.

Answer: For each line, here is the appropriate option from A to E that applies:

All internal works to be assigned to Timber Tigers throughout the project should be consolidated into one Structured Timebox.

E. False (Assertion) False (Reason)

Rationale: It is not practical or in line with Agile principles to consolidate all internal works into one Structured Timebox, as the work will likely need to be spread over multiple Timeboxes. Additionally, the Investigation step involves agreeing on how to meet the requirements of the Timebox, not necessarily consolidating all work into one.

Acceptance criteria for the front rooms to be developed in Timebox A should be described in detail and agreed during the Timebox Kick-Off

B. True (Assertion) True (Reason) BUT the reason does not explain the assertion

Rationale: While it is true that acceptance criteria should be agreed upon during the Timebox Kick-Off, the reason given is incorrect because the aim of the Investigation step is not necessarily to complete as much development work as possible but to plan and understand the work that will be carried out.

It is appropriate that both the Evolutionary Development phase and Deployment phase are shown in the first Project Increment.

A. True (Assertion) True (Reason) AND the reason explains the assertion

Rationale: Each Timebox should indeed include both Evolutionary Development and a Deployment phase. This assertion and reason correctly align with the concept of Timeboxing in Agile.

It is appropriate that the outputs of Timebox C are scheduled for deployment at the end of the first Project Increment.

A. True (Assertion) True (Reason) AND the reason explains the assertion

Rationale: The typical Timebox Plan does provide a schedule of high-level activities for the imminent Project Increment, which would include planning for deployment.

It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.

C. True (Assertion) False (Reason)

Rationale: While it is true that Earth Excavations should create a detailed plan for their activities in Timebox C, the reason is incorrect as the Solution Development Team is not solely responsible for planning all work details within a Timebox. This task would typically be a collaborative effort involving all relevant parties.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments