Which is an appropriate response if there are unfinished items in the Sprint Backlog by the end of the Sprint time-box? (Choose the best answer)
Which is an appropriate response if there are unfinished items in the Sprint Backlog by the end of the Sprint time-box? (Choose the best answer)
A . The Sprint time-box holds and the Scrum Team continuously learns what is actually possible to do within a time-box and adapts.
B . The Sprint extends until all items are completed.
C . Immediately transition to Kanban.
D . The current time-box is adjusted and all future Sprints will comply to the new time-box.
Answer: A
Latest PSPO-III Dumps Valid Version with 65 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments