What’s the immediate SAFe tip you would implement to ensure that value is delivered sooner?
You’re managing a team that has embodied SAFe. It takes about 5 days for each of your internal clients’ requests for a feature to be answered by the development lead and, on average, only about 2 days to implement a feature. The testing team also takes another day, but the handover from development to testing takes two days per feature request.
What’s the immediate SAFe tip you would implement to ensure that value is delivered sooner?
A . Remove, or minimize, the implementation time.
B . Remove the development lead and educate a self-organizing team.
C . Have the developers carry out the testing of their own work and remove the testing team completely.
D . Remove, or minimize, the request wait time and the testing handover time.
Answer: D