What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.
What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.
A . Order type
B . Planning strategy
C . Requirements profile
D . Requirements type
Answer: B, C