Architects are typically accountable for which measures at the end of the PI?
Architects are typically accountable for which measures at the end of the PI?
A . ART velocity and predictability
B . Business value scores of Enabler Features and Capabilities
C . Return of Investment of delivered Architectural Runway
D . Architectural compliance metrics
Answer: B
Explanation:
Business value scores of Enabler Features and Capabilities