What is their normalized velocity before calculating for time off?

The Scrum Master wants to establish a team’s initial velocity. A team has two testers, three developers, one full-time Scrum Master, and a Product Owner split between two teams.

What is their normalized velocity before calculating for time off?
A . 40
B . 32
C . 48
D . 52

Answer: A