Which artifacts are created within application design and configuration workstream in the explore Phase of the "New implementation of SAP S/4HANA" There are 3 correct answers to this question

Which artifacts are created within application design and configuration workstream in the explore Phase of the "New implementation of SAP S/4HANA" There are 3 correct answers to this question
A . Project procedure-mock-up modeling
B . Roles and authorizations management concept
C . Delta requirements list-register
D . Detailed design-business process
E . Organisation structure specification

Answer: B C, D