What should you do?

You need to ensure that the data is updated to meet the report requirements. The solution must minimize configuration effort.

What should you do?
A . From each report in powerbi.com. select Refresh visuals
B . From Power Bl Desktop, download the PBIX file and refresh the data.
C . Configure a scheduled refresh without using an on-premises data gateway.
D . Configure a scheduled refresh by using an on-premises data gateway

Answer: C