What settings should you make to ensure precise scheduling is used when the system performs delivery scheduling? Note: There are 3 correct answers to this question.
What settings should you make to ensure precise scheduling is used when the system performs delivery scheduling? Note: There are 3 correct answers to this question.
A . Maintain the transit time in the route in hours and minutes.
B . Assign a set of working times to the plant.
C . Maintain shifts defining the times for starting and ending work.
D . Assign a shift sequence to the working times.
E . Assign a set of working times to the shipping point.
Answer: B, C, E