CompTIA PK0-005 CompTIA Project+Certification Online Training
CompTIA PK0-005 Online Training
The questions for PK0-005 were last updated at Nov 22,2024.
- Exam Code: PK0-005
- Exam Name: CompTIA Project+Certification
- Certification Provider: CompTIA
- Latest update: Nov 22,2024
A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks.
Which of the following should be used to document this information?
- A . RFI
- B . RACI
- C . WBS
- D . SOW
A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the communicated expectations.
Which of the following tools should the project manager use to validate the functionality?
- A . Project status report
- B . Requirements Traceability Matrix
- C . Detect log
- D . Signed project charter
- E . Work breakdown structure
When introducing a new information asset, what is the MOST important responsibility of the asset owner?
- A . Information disposal
- B . Information classification
- C . Information access administration
- D . Information backup
A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project’s production run will be delayed from the beginning.
Which of the following dependencies is most likely happening?
- A . Finish-to-start
- B . Start-to-start
- C . Finish-to-finish
- D . Start-to-finish
A project manager is monitoring team performance by comparing committed versus completed work.
The project manager creates the following:
Which of the following most likely represents the number of items in the backlog?
- A . 23
- B . 5
- C . 10
- D . 15
A project team is working on a document to precisely describe the success criteria that should be fulfilled by a product.
Which of the following documents is the team preparing?
- A . Project scope
- B . Quality plan
- C . Contract obligations
- D . Work breakdown structure
A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation.
Which of the following is MOST likely happening?
- A . Scope creep
- B . Collecting requirements
- C . Decision-making
- D . Project change
A financial manager reports that several employees’ allocations from the past month appear to be 200% even though they are only assigned to a particular project.
Which of the following could MOST likely be the cause of this issue?
- A . A project manager assigned the wrong resources.
- B . A project manager did not release the resources
- C . A project manager did not remove the system access.
- D . A project manager did not provide the project sign-off.
During quality analysis, different team members are identifying multiple constraints.
Which of
the following tools should the project manager adopt first to help track and prioritize a resolution?
- A . Issue log
- B . Defect log
- C . Risk register
- D . Change log
A project manager wants to schedule a troubleshooting session for team members who are located in Germany and California.
Which of the following is most important for the project manager to consider when setting up the session?
- A . Cultural differences
- B . Technological factors
- C . Time zones
- D . Language barriers