What should you be aware of when running the Create Time Periods application job?
You need to create time periods for the time profile in a planning area.
What should you be aware of when running the Create Time Periods application job?
A . The assigned Planning Area must be active.
B . This application job can be run for multiple time profiles at once.
C . In the Parameter Section of the application job, choose the Time Profile ID and Planning Area.
D . A time profile has to be activated so that the application job can proceed.
Answer: C