What will you need to do to set them up with the proper work calendar?
You are in the process of setting up your organization’s Resources and learn that Resources in France will be working a 35-hour work week.
What will you need to do to set them up with the proper work calendar?
A . As PSA only allows one work calendar, it is best to implement a 40-hour work calendar and then create a validation rule to only allow 35 hours a week.
B . As the Work Calendar mostly impacts Utilization, set them up with a 40-work calendar, and then include the 35-hour hour work week in your utilization calculations.
C . Create a separate 35-hour work calendar and associate it to the French Resources, including any specific French Holidays.
Answer: C