Based on the SAP Activate methodology, which activities must you perform in the Explore phase?
You reviewed the project scope and identified the corresponding resources.
Based on the SAP Activate methodology, which activities must you perform in the Explore phase? (2 correct)
A . Conduct the Fit-to-Standard workshops to identify fits, gaps, and perceived gaps
B . Use the Quality system to demonstrate SAP Best Practices processes
C . Use the Starter system to demonstrate SAP Best Practices processes
D . Configure the organizational structure and chart of accounts in the system
Answer: B, C