When you enter a priority during creation of notification, what can the system do?

You define a priority type in the implementation guide (img) and assign it to a notification type.

When you enter a priority during creation of notification, what can the system do?
A . Send one or more e-mails to involved partners
B. Start workflow to inform the responsible person(s)
C. Create one or more task automatically
D. Calculate the notification start and finish dates.

Answer: D

Explanation:

In SAP, when you define a priority type in the Implementation Guide (IMG) and assign it to a notification type, entering a priority during the creation of a notification allows the system to:

Option D. Calculate the notification start and finish dates.

The priority type can influence the urgency and timeline of the notification, allowing the system to determine appropriate start and finish dates based on the priority set.