Which implementation approach is the LEAST appropriate in this situation?

A record company is implementing a new system to replace an existing legacy system. The project has challenging as the new system must be implemented before support for the existing system is withdrawn. The business users have been involved throughout the project and their confidence in the new system is high.

Which implementation approach is the LEAST appropriate in this situation?
A . Pilot
B. Phased
C. Direct changeover
D. Parallel running.

Answer: C

Latest MBPv6 Dumps Valid Version with 40 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments