Which of the following must be in place before implementing a BCP?
Which of the following must be in place before implementing a BCP?
A . SLA
B. AUP
C. NDA
D. BIA
Answer: D
Explanation:
A Business Impact Analysis (BIA) is a critical component of a Business Continuity Plan (BCP). It identifies and prioritizes critical business functions and determines the impact of their disruption.
Reference: CompTIA Security+ Study Guide 601, Chapter 10