What should the project manager do first?

A project manager is working on a large IT project. During a review for one of the deliverables, a stakeholder raised a concern about the final product.

What should the project manager do first?
A . Set up a meeting with the product owner to discuss the stakeholder’s concern.
B. Discuss this with the team and review the project requirements documentation.
C. Set up a meeting with the sponsor to discuss the details of the deliverable.
D. Discuss this with the team and put the stakeholder’s concern in the issue log.

Answer: A