What can they learn from this chart?
Razi’s team just completed their first sprint.
What can they learn from this chart? (Choose three.)
(Assume Remaining Estimate and Time Spent is disabled for this board.) This sprint ends with 0 story points.
A . There are 2 issues resolved on July 8th.
B. Some of the issues are still unresolved.
C. This sprint starts with 20 story points.
D. Some of the issues are resolved during non-working days.
E. There are no scope changes in this sprint.
Answer: C,D,E
Explanation:
The grey area indicates days that are non-working days. Some issues were resolved during non-working days since story points were reduced in the grey area.
This chart starts drawing the ‘guideline’ and ‘remaining values’ lines at the 20 story points on the y-axis.
Meaning, this sprint starts with 20 story points.
The ‘remaining values’ line ends with 2.5 story points. Therefore, some issues are still unresolved in this sprint.
Story points do not increase during this sprint. Since the remaining estimate and time spent is disabled for this board, scope change is not indicated in the Burndown Chart for the subtask. We cannot confirm if there are no scope changes in this sprint.