Which of the following are true?

Nash is creating a new Scrum board with multiple Jira projects. Each project has a different status in its workflow.

Which of the following are true? (Choose two.)

A. Some issues will be hidden from the board.

B. The user cannot create a new board with multiple Jira projects.

C. All statuses will be mapped to 3 default columns: To Do, In Progress, and Done

D. All issues will be hidden from thewwwboard.dumpspanda..com

E. The status will be mapped to the first selected project when creating the new board.

Answer: A C

Explanation:

A. Some issues will be hidden from the board.

When you create a new board that includes multiple projects with different workflows, the board’s column configuration will not necessarily include all statuses from all the workflows by default. As such, any issues with statuses that aren’t mapped to a column on the board will not be visible on the board.

C. All statuses will be mapped to 3 default columns: To Do, In Progress, and Done

When a new board is created, Jira creates three default columns: To Do, In Progress, and Done. Initially, it tries to map the statuses of the issues to these columns based on the nature of the status. However, if there are unique or custom statuses in the workflows of the projects, you may need to manually adjust the column configuration to ensure all statuses are mapped to a column.