Which of the following are true about epic? (Choose two.)
Which of the following are true about epic? (Choose two.)
A . An epic can have another epic. (Epic Link)
B. An epic cannot have its own issue screen.
C. An epic cannot convert to a sub-task.
D. Users need to enable Kanban Backlog to use Epic in the Kanban Board.
E. Users can customize Epic’s colour in both Kanban and Scrum projects.
F. An epic can have issues that belong to more than one project.
Answer: C,F
Explanation:
Options C An epic cannot convert to a sub-task.
Sub-tasks are intended to be smaller parts of a standard issue, not a larger construct like an epic. While you can convert issues to epics and vice versa, it’s not possible to convert an epic directly into a sub-task, as they serve different functions and have different hierarchical levels.
Options F An epic can have issues that belong to more than one project.
In Jira, an epic is a large body of work that can be broken down into a number of smaller stories, or sometimes called "issues". It’s possible for these issues to belong to more than one project, which allows for cross-project tracking and management.