What do you check?
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling.
What do you check? Note: There are 2 correct answers to this question
A . If the maximum reduction level is less than 100
B. If the reduction strategy is set in the network header
C. If the reduction strategy is set in each activity
D. If the appropriate reduction type is set in the parameters for network scheduling
Answer: A,D