Which statements apply to the maintenance of the actual start and finish?
You are using WBS elements and activities are NOT assigned.
Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question
A . You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released"
B. You can always maintain the actual start if the WBS element has the status "Released" or "Partially released"
C. You can always maintain the actual start and finish date of a WBS element
D. You can only maintain the actual start of a WBS element if the finish date is not maintained
Answer: B,C
Latest C_TS412_2021 Dumps Valid Version with 112 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments