What is the effect on the planned production orders when you enable the Planning Optimization feature?

Topic 7, Misc. Questions

A manufacturing company uses Planning Optimization. Manned production orders are created, modified, and approved by the

planner but are not yet firmed.

What is the effect on the planned production orders when you enable the Planning Optimization feature?
A . Modifications are ignored when Planning Optimization is run again.
B. Modifications are included when Planning Optimization is run again.
C. Approved orders are automatically firmed.
D. Approved orders are set to unprocessed.
E. Approved orders are set to completed.

Answer: B

Explanation:

https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/planning-optimization/purchase-trade-agreement