What is used to assess the program cost/benefit justification?
Program manager B leaves the program and program manager A takes over the program responsibilities Program manager A wants to ensure that all expected benefits of the program are realized.
What is used to assess the program cost/benefit justification?
A . Program charter
B. Benefits management plan
C. Program business case
D. Program scope statement
Answer: C