What should the program manager do first?

Company A acquires company B. which leads to a two-year program lo integrate the processes and systems Company B uses a different project management process, and the company’s staff is unhappy about the acquisition As a result company B’s project team fails to provide status and cost data in a format that conforms to the program standards.

What should the program manager do first?
A . Inform the stakeholders of this Issue as soon as possible
B. Change the program standards, aligning them with the project standards
C. Work with the reports provided to extract the required information
D. Remind the project manager of the relevant program standards

Answer: D

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments