As part of the designer’s responsibilities, which two of the following ate key elements of the Kick-off Meeting?

A project’s installation start involves a Kickoff Meeting and the General Contractor’s Coordination Meeting.

As part of the designer’s responsibilities, which two of the following ate key elements of the Kick-off Meeting? (Select two options.)
A . Project submittal approval process
B. RFI process
C. Payment procedures
D. Punch List process
E. Project start and completion dates

Answer: B,E