What should be done with the identified potential risk?
Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team’s attention.
What should be done with the identified potential risk?
A . Incorporate it into the risk register and perform a thorough analysis
B. Mitigate the risk before it is incorporated into the risk management plan
C. Document the risk in the program transition plan and identify it as a potential issue
D. Document it m the issue log and immediately notify the steering committee
Answer: A