How should the project manager address this concern?
Several key stakeholders approach the project manager with concerns. The stakeholders have received feedback from local businesses that have reported a reduction in customers because of construction activities at the worksite, and they plan to submit a claim to the municipality to fine the project manager’s company.
How should the project manager address this concern?
A . Evaluate the risk with the team and update the issueing
B. Discuss the concern with the local business owners.
C. Update the key risks and perform a quantitative risk analysis.
D. Adjust construction work hours to after business hours.
Answer: A
Explanation:
The project manager should evaluate the risk with the team and update the issueing to address the concerns of the stakeholders and local businesses.