Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct answers to this question
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct answers to this question
A . Planned revenue requires a sales order assigned to a WBS element
B. Planned revenue can be transferred from a sales quotation
C. Actual revenue is posted via a billing plan assigned to a WBS element
D. Actual revenue is posted via a billing document created from a sales order
Answer: B,C
Latest C_TS412_2021 Dumps Valid Version with 112 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments