What is a strategy a Product Owner can use during Program Increment Planning to minimize dependencies?

What is a strategy a Product Owner can use during Program Increment Planning to minimize dependencies?
A . Change the definition of done
B. Move Stories on their team’s backlog to another team
C. Reprioritize Epics

Answer: B

Explanation:

Dependecy can be addressed through ROAMing activity, if story is depending on other team, then PO can move story on another teams backlog.

Latest SASM Dumps Valid Version with 185 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments