How are the program risks, that have been identified during Pl Planning, categorized?

How are the program risks, that have been identified during Pl Planning, categorized?
A . Resolved, Owned, Accepted, Mitigated
B. Resolved, Owned, Acknowledged, Managed
C. Removed, Owned, Accepted, Managed
D. Removed, Owned, Acknowledged, Mitigated

Answer: A

Explanation:

Risk are categorized into: Resolved, Owned, Accepted, Mitigated