Which three of the following criteria are most helpful as part of a Scrum Team’s Definition of Done? (choose best three answers)

Which three of the following criteria are most helpful as part of a Scrum Team’s Definition of Done? (choose best three answers)
A . Code Review is done.
B. Acceptance Tests pass.
C. The Product is released at the end of every Sprint.
D. No impediments exist.
E. Regression Tests pass.

Answer: A,B,D