Which set of actions meets these criteria?

A network engineer configures the Cisco ACI fabric to connect to vCenter with these requirements:

Port groups must be automatically created on the distributed virtual switch.

Port groups must use the VLAN allocation in the range between 20-30.

The deployment must optimize the CAM space on the leaf switches.

Which set of actions meets these criteria?
A . Create a dynamic VLAN pool with the VLAN range of 20-30.
Create a VMM domain and associate it with the VLAN pool.
Create the EPG and associate the domain.
Set the deployment immediacy to On Demand.
B. Create a dynamic VLAN pool with the VLAN range of 20-30.
Create a physical domain and associate it with the VLAN pool.
Create the EPG and associate the domain.
Set the deployment immediacy to On Demand.
C. Create a static VLAN pool with the VLAN range of 20-30.
Create a physical domain and associate it with the VLAN pool.
Create the EPG and associate the domain.
Set the deployment immediacy to Immediate.
D. Create a static VLAN pool with the VLAN range of 20-30.
Create a VMM domain and associate it with the VLAN pool.
Create the EPG and associate the domain.
Set the deployment immediacy to Immediate.

Answer: A