How should the administrator accomplish this?

An administrator has two clusters: Site A and Site B.

Async DR is configured between the clusters as follows:

• Site A is the Primary Site

• Site B is the Secondary inactive Site, no VMs running

• Site A is fully in Production

• Site B used as Backup/Disaster Recovery

The customer wants to perform a planned failover between the sites.

How should the administrator accomplish this?
A . Click Activate on the Secondary site within the Data Protection Dashboard
B. Click Activate on the Secondary site and run deactive NCLI command on Primary site
C. Choose Migrate on the Secondary site within the Data Protection Dashboard
D. Choose Migrate on the Primary site within the Data Protection Dashboard

Answer: D

Explanation:

Reference: https://portal.nutanix.com/page/documents/details?targetId=Web-Console-Guide-Prism-v510:wc-protection-domain-failover-wc-t.html