How should the administrator perform this task?
An administrator needs to forecast infrastructure requirements for a new program and its associated applications. Prior to the projected start of the new program, all existing applications will be decommissioned.
How should the administrator perform this task?
A . Check the Disregard Existing Workloads radio button in the Runway scenario.
B. Check the Disregard Existing Nodes radio button in the Runway scenario.
C. Add up the recovered workloads and manually remove from the Runway configuration.
D. Power down the workloads during a maintenance window and run the Capacity Runway.
Answer: A