Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:

Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:
A . Enterprise environmental factors
B. Work performance reports
C. Organizational process assets
D. Context diagrams

Answer: A