Which tool or technique is used in validating the scope of a project?
Which tool or technique is used in validating the scope of a project?
A . Facilitated workshops
B. Interviews
C. Inspection
D. Meetings
Answer: C
Latest CAPM Dumps Valid Version with 1089 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments