How often should the Nexus Sprint Backlog be adjusted?
How often should the Nexus Sprint Backlog be adjusted?
A . At least every Nexus Daily Scrum
B. Only during Sprint Planning
C. Once a week
Answer: A
Explanation:
At least every Nexus Daily Scrum, the Nexus Sprint Backlog should be adjusted to reflect the current understanding of the work of the Scrum Teams within the Nexus.